Based on demographic projections, Aledo Middle School will exceed maximum student capacity in one year (2020-2021). The Bearcat Growth Committee addressed the enrollment growth and capacity at the middle school level by building a bond package that includes a new Middle School #2 and a large-scale renovation/expansion of the current Aledo Middle School.
Renovations to Aledo Middle School will include a new library, fine arts wing, gym, field house and new cafeteria space. Aledo ISD will shift to a 6th-8th grade configuration at the middle school level. Currently, McAnally Intermediate serves all Aledo ISD 6th grade students.
Aledo Middle School originally opened in 1967 as a high school and middle school. It became AMS after the current high school was built in 2000 and the front wing addition opened in 2002.
Scope of Work
- Architect: Huckabee
- Construction: Imperial Construction
- Grade-level 6-8th Academic Wings (1,200 student capacity)
- Reuse of front 2002 wing (with renovations), multi-purpose center (gym), stadium
- Fine Arts Wing
- Cafeteria space renovation
- Fieldhouse replacement
- Cost $33,446,000
Tentative Project Schedule
Design: January 2020-November 2020
Procurement: December 2020-January 2021
Construction: February 2021-August 2022
School opens: August 2022