Aledo ISD Early Childhood Academy (Vandagriff Renovation - Early Childhood Campus)
Vandagriff Renovation - Early Childhood Campus
The voter-approved bond includes Vandagriff Elementary being renovated into an Early Childhood Campus ($1.7 million) serving children in the District’s Pre-Kindergarten program and Preschool Program for Children with Disabilities, with a planned expansion of the District’s early childcare program for employees’ children. The renovation includes the demolition of the annex. McAnally will be renovated to become an Elementary School ($9.6 million) and will replace Vandagriff.
Vandagriff opened in 1964 and was expanded in 1995. The annex opened in 1957.
Scope of Work
- Architect: PBK
- Construction: TBD
- Serve all early childhood programs
- Roof, site drainage repairs
- Demolition of 1957 annex
- Cost $1,709,000
Tentative Project Schedule
Design: February 2021-March 2021
Procurement: April 2021-May 2021
Construction: May 2022-July 2022
School opens: August 2022
Children Served: Early childhood programs, childcare for employees' children