Based on demographic projections, Aledo ISD's maximum elementary school capacity will be exceeded in two years (2021-2022). The new Elementary School #6 will be located on district-owned property on FM 5 in Annetta on the southwest side of the District.
Elementary #6 includes $3.3 million for FM 5 roadway improvements and water/wastewater infrastructure, which is an included cost in the overall campus amount.
Please note: This is an early rendering concept of Elementary #6.
Scope of Work
- Architect: PBK
- Construction: Satterfield & Pontikes (S&P)
- Shared grade-level collaborative learning spaces
- Located on FM 5 across from Annetta Cemetery
- FM 5 road improvements & water/wastewater infrastructure
- Cost $35,858,000
Tentative Project Schedule
Design: January 2020-May 2020
Procurement: May 2020-July 2020
Construction: August 2020-July 2021
School opens: August 2021
Grades Served: Kindergarten-5th grade