Middle School No. 2

  • Based on demographic projections, Aledo Middle School will exceed maximum student capacity in one year (2020-2021). The Bearcat Growth Committee addressed the enrollment growth and capacity at the middle school level by building a bond package that includes a new Middle School #2 and a large-scale renovation/expansion of the current Aledo Middle School. Aledo ISD will shift to a 6th-8th grade configuration at the middle school level. Currently, McAnally Intermediate serves all Aledo ISD 6th grade students.

    Middle School #2 will be located on Old Weatherford Road and includes $1.5 million for roadway improvements, which is an included cost in the overall campus amount.

    Scope of Work

    • Architect: Huckabee
    • Grade-level 6-8th Academic Wings (1,200-student capacity)
    • Fine arts & athletic facilities sized for Aledo ISD programs
    • Old Weatherford Road improvements
    • Cost $62,501,000


    Tentative Project Schedule
    Design: March 2020-October 2020
    Procurement: November 2020-December 2020
    Construction: January 2021-July 2022
    School opens: August 2022
    Grades Served: Grades 6-8th